This week we had a meeting with Jason, who within 10 minutes of requesting a meeting on-site to discuss some issues arranged to meet later the same afternoon - can't say they have been unresponsive and uncaring, because so far every question answered and every request has been approved.
Jason cleared up a lot of our concerns regarding the framing/footings, and said once the frame punch is done we should see a much better condition.
Also a result from our last blog post - they were perfectly happy swapping the closet/bathroom in the guest suite downstairs and therefore making the windows in line - it means we aren't getting four windows as per the elevation but at least they wont make the back look weird!
At the start of the week, we were told the trades would be starting, well by the end of the week it looks like all the plumbing is DONE and what looks like most of the HVAC done as well. Electrics is slightly different, guessing that'll be next week.
Today we went round to take some pictures and there was someone there putting our study window in and moving the window out of the guest suite closet into the new hole in the bathroom...
Also took us quite by surprise but our deck is UP! A few pictures from outside:
Jason cleared up a lot of our concerns regarding the framing/footings, and said once the frame punch is done we should see a much better condition.
Also a result from our last blog post - they were perfectly happy swapping the closet/bathroom in the guest suite downstairs and therefore making the windows in line - it means we aren't getting four windows as per the elevation but at least they wont make the back look weird!
At the start of the week, we were told the trades would be starting, well by the end of the week it looks like all the plumbing is DONE and what looks like most of the HVAC done as well. Electrics is slightly different, guessing that'll be next week.
Today we went round to take some pictures and there was someone there putting our study window in and moving the window out of the guest suite closet into the new hole in the bathroom...
Also took us quite by surprise but our deck is UP! A few pictures from outside:
Some images of the pipework on the first floor...
We have definitely decided once the frame punch is done and all the trades are complete (i.e. pre dry wall meeting/inspection) we will go and take our best camera around and document the house - these pictures are very valuable knowing where all the pipes are etc.
The following are some pics of the basement with a bunch more pipes/ducts.
The following are some pics of the basement with a bunch more pipes/ducts.
Finally the following is some pics of plumbing upstairs (and our study window since they had literally just installed it!)