- June 8th - Breaking ground and Footings
- June 15th - Concrete Foundation and Basement walls poured
- June 22nd - Drainage and Insulation around foundation and gravel
- June 29th - Basement plumbing and Back-filling
- July 6th - More back-filling - basement gravel and garage.
- July 13th - Concrete - Basement + Garage
- July 20th - Framing - Basement + Garage
- July 27th - Roof, Shingles and cut out missing window holes
- August 3rd - Windows / Stairs / Shingles
- August 10th - Trades: Beginning Plumber/HVAC (Update to completion - start-mid November!)
- August 17th - Frame Punch Check - Plumbing/HVAC finish
- August 24th - Electrician start - final windows
- August 31st - Low Voltage (Central Vac, Cable, Phone etc), Trades Continue
- September 7th - Finish Pre-Dry wall trades (Update to completion - mid-October - start November)
- September 14th - Framing inspection, Siding started, Pre-Dry Wall meeting + Dry Wall started
- September 21st - Insulation Fixes/Framing Fixes, Siding Started, Dry wall Starting (Most delayed due to inspections failing)
- September 28th - Siding actually started, Drywall finished/mud starting
- October 5th - Finish Siding / Finish Drywall - Possible Cabinets
- October 12th - Cabinets started, Driveway poured, trim and tile
- October 19th - Siding Finished(!), Driveway poured(!), Interior Trim
- October 26th - Interior Trim continue + Painting Started
- November 2nd - Finish Trim/Painting (Bad weather means exterior still on hold)
- November 9th - Exterior/Interior Stonework, plumbing completed
- November 16th - Kitchen Tile, Flooring, Carpet, Door Hardware, Wall Punch List start
- November 23rd - Electric hook up, Paint Touch Up, Landscaping start
- November 30th
- December 7th ** Scheduled Close 9th December **
- December 14th
- December 21st
- December 28th
Hoping and Praying we will not be having calls in to 2016!